REMIT Data

by station




Urgent Market Messages
(UMM)
(To see further urgent market messages and historical information please click on the affected unit in question)
Affected
unit
Published
DateTime
Event
Type
Event
Status
EventStart
DateTime
EventEnd
DateTime
Available
Capacity
(MW)
Message ID Cause Related Information
T_EGGPS-1 11/02/2017
08:49AM
Unplanned Ongoing 11/02/2017
08:47AM
11/02/2017
13:30PM
400 SBR Proving Run
T_EGGPS-2 11/02/2017
08:50AM
Unplanned Ongoing 11/02/2017
08:49AM
11/02/2017
14:00PM
375 SBR Proving Run
T_EGGPS-3 26/04/2017
11:37AM
Planned Ongoing 26/04/2017
11:35AM
01/05/2017
00:00AM
0 Planned Outage
T_EGGPS-4 17/03/2017
16:04PM
Planned Superseded 17/03/2017
16:03PM
19/06/2017
07:00AM
0 Planned Outage
Planned Outages *1
Asset ID Available
Capacity
(MW)
Start
DateTime
End
DateTime
T_EGGPS-1 0 01/04/2017
00:00AM
01/10/2017
00:00AM
T_EGGPS-2 0 01/04/2017
00:00AM
01/10/2017
00:00AM
T_EGGPS-3 0 01/05/2017
00:00AM
30/09/2017
23:59PM
T_EGGPS-4 0 17/03/2017
00:00AM
19/06/2017
07:00AM
Static Data *2
Asset ID Normal
Capacity
(MW)
Fuel Type Location Market
T_EGGPS-1 490 Hard Coal Goole GB BETTA Market
T_EGGPS-2 480 Hard Coal Goole GB BETTA Market
T_EGGPS-3 495 Hard Coal Goole GB BETTA Market
T_EGGPS-4 495 Hard Coal Goole GB BETTA Market


It should be noted that for the Winter 2016/17, Units 1 and 2 at Eggborough Power Station, are contracted to run in SBR.
Further information on SBR can be found on National Grid’s website. 

Unless otherwise advised by Eggborough Power Station, where the NDZ published by Elexon is at 999,  the NDZ as published below should be used.
 
Current NDZ SBR Units – 2,880 minutes
 

From Monday  27th February 2017 Eggborough Power Station will not be running T_EGGPS-3 and T_EGGPS-4 concurrently  and will make an election as to which unit will generate having regard to technical  and operational considerations.  

Eggborough Power Station has been provisionally awarded a Capacity Agreement from the EMR Delivery Body for the delivery year 1st October 2017 to September 30th 2018 and its availability is currently subject to a final award of a Capacity Agreement.


*1 Planned Outages This data identifies planned outages for Eggborough Power Ltd's UK generating units of equal to or greater than 100MW capacity for the timescale of 2 days ahead to 1 year ahead. This data will be updated within an hour of a firm change of availability.

*2 Static Data This data below provides further details of Eggborough Power Ltd's UK generating units of equal to or greater than 100MW capacity. GC represents the Generating Capacity of a generating unit as defined by Elexon. The Fuel Type defines the primary fuel used for firing each unit.